Our Services
Upgrade Existing Sewer Mains
Sewer upgrades are required when the existing main cannot accommodate future demand. This often involves increasing the pipe size to handle higher sewage flow.
π Example Scenario:
- Existing sewer: 150mm
- New sewer: 225mm
- Upgrade length: 300m
- Location: Urban area, under a roadway
Each project has unique challenges, making site visits crucial for accurate estimating.
1. Key Factors in Sewer Upgrade Estimates
πΉ Pipe Size & Length:
- Designers specify the exact length of the upgrade and the new pipe size.
- The upgrade may involve new manholes if spacing needs to change.
πΉ Depth & Excavation Constraints:
- The deeper the sewer, the more complex and expensive the installation.
- Excavation width depends on the pipe size and soil conditions.
- If trench walls cannot be benched out, shoring boxes must be used for safety.
πΉ Site Constraints & Traffic Conditions:
- If the upgrade is in the middle of a road, extensive traffic control is required.
- Narrow streets, busy roads, or pedestrian areas complicate work planning.
- Overhead powerlines or underground utilities require additional precautions.
πΉ Machinery & Crew Requirements:
- The right excavator size depends on depth and material type (rock, clay, sand, etc.).
- Additional machinery such as vacuum trucks may be needed for utility exposure.
- Crew size must be sufficient to handle excavation, installation, and backfilling efficiently.
2. Site Visit β Why Itβs Essential for Cost Accuracy
A physical inspection of the job site helps answer key questions:
β
Is there enough space for excavation and stockpiling material?
β
Will benching work, or do we need shoring boxes?
β
Are there any obstacles (overhead powerlines, underground utilities, trees, structures)?
β
Will we need extensive traffic control and road closure permits?
β
Where will excavated material be taken, and how much disposal will cost?
π Site conditions significantly affect costs. A thorough inspection avoids surprises later.
3. Excavation & Shoring Costs
πΉ Depth Considerations:
- If the sewer depth is over 3m, Level 1 Geotechnical supervision is mandatory.
- The deeper the trench, the more expensive the excavation and safety requirements.
πΉ Shoring vs. Benching
- If there’s enough space, trench walls can be benched to prevent collapse.
- If space is limited (e.g., in a roadway), shoring boxes must be used for worker safety.
- Shoring rentals and installation time must be factored into costs.
πΉ Excavator Selection:
- Small jobs (shallow trenches): 5Tβ14T excavators.
- Medium-depth sewers (2mβ3m): 14Tβ20T excavators.
- Deep sewers (3mβ6m+): 30Tβ50T excavators (especially for rock excavation).
Β
πΉ Material Type & Excavation Difficulty:
- Rock excavation is significantly more expensive than clay or sand.
- Different soil conditions (clay, shale, sand, etc.) affect digging speed and disposal costs.
- Vacuum excavation may be required if working near existing utilities.
4. Traffic Control & Roadway Costs
If the sewer upgrade is in or near a roadway, extensive traffic management is needed:
πΉ Traffic Control Measures & Fees:
- Traffic Management Plan (TMP) β Council approval required.
- Road opening fees & permits β Paid to local councils.
- Road occupancy fees β If lanes must be closed.
- Reinstatement bonds β Refundable but must be accounted for upfront.
- Night works (if required) β Higher labor costs.
π Traffic control costs can be substantial β they must be included in the estimate.
5. Disposal & Material Costs
πΉ Spoil Disposal:
- Excavated material cannot be reused in roads β select fill must be imported.
- Tip fees depend on material type β general waste, clean fill, contaminated soil, etc.
- If disposing of old pipes or concrete manholes, costs vary based on contamination levels.
πΉ Pipe & Bedding Materials:
- Sewer mains require select bedding material (e.g., Blue Metal).
- Pipe type (e.g. PVC, PE) impacts material costs.
6. Testing & Compliance
πΉ Level 1 Geotechnical Supervision (if depth >3m)
πΉ Compaction testing every 150mm layer
πΉ Hydrostatic or air pressure testing for new pipes
πΉ CCTV inspection of completed sewer upgrade
π All testing fees must be included in the estimate.
7. Summary β Estimating Sewer Upgrade Costs Accurately
β Confirm upgrade details from the designer β length, new pipe size, manholes.
β Conduct a site visit β assess space, depth, existing services, traffic impact.
β Plan excavation method β benching vs. shoring, excavator size, ground conditions.
β Account for traffic control & council fees β road opening, occupancy, reinstatement bonds.
β Estimate disposal costs β confirm tip fees for different materials.
β Include material & labor costs β select bedding, pipe materials, crew size.
β Factor in all testing requirements β geotech supervision, compaction, pipe testing, CCTV.
π° A detailed and well-researched estimate prevents cost overruns and ensures profitability.
At WSE Sydney, we specialize in accurate estimating for sewer upgrade projects, ensuring all costs are properly accounted for.
π§ tenders@watersewerestimatingsydney.com.au
π +61 451 404 645
