Our Services
Insert Sewer Junction Estimates
πΉ For New/Proposed Sewer (Simple & Low Cost)
- Junctions are installed while laying the new sewer pipe.
- No additional excavation or cutting required.
- Standard costs for pipe materials, excavation, and backfill.
πΉ For Existing Sewer (Complex & Expensive)
- Cutting a junction into an existing sewer is far more complicated.
- Multiple risks, unexpected site conditions, and time-consuming work.
- Requires detailed investigation & careful estimation.
2οΈβ£ Key Steps for Estimating an Existing Sewer Junction
π Step 1: Initial Investigations
β Dial Before You Dig (DBYD) & Existing Sewer Records
- Check pipe size, depth, material, and any existing encasement.
- Identify any structures or obstacles nearby.
β Site Visit & Utility Locating
- Confirm depth and access issues.
- Look for any surface constraints (roads, footpaths, buildings, trees, other utilities, etc.).
π Step 2: Excavation & Shoring
β Excavation Method Selection
- Standard digging (if ground conditions allow).
- Hand digging or vacuum excavation (if working near live services).
- Rock breaking (if required).
β Shoring or Benching Costs
- If the depth is over 1.5m, allow for shoring hire costs.
- In tight spaces, trench shields or steel shoring boxes may be required.
π Step 3: Exposing the Existing Sewer Pipe
β Check for Unexpected Encasement
- If the pipe is concrete encased, additional jackhammering & concrete removal is needed.
- If the pipe is not encased, work is simpler β but confirm this with qualifications in pricing!
β If Sewer was Originally Bored:
- Existing sewer may be inside a steel casing pipe.
- Cutting the steel casing requires special tools.
- Inside the casing, there may be grout fill (which is basically solid concrete now).
- Breaking through grout fill is another time-consuming step.
π Step 4: Cutting & Installing the Junction
β Pipe Material Considerations
- OPVC/DICL Pipes: Standard cutting methods.
- MSCL Pipes: May require welding & hot works permits.
- Concrete Pipes: May require core drilling before installing the junction.
β Backfilling & Compaction Testing
- Backfilling carefully to avoid damaging the new junction.
- Compaction testing every 150mm lift (mandatory in Sydney Water projects).
3οΈβ£ Hidden Costs & Risks
β Unexpected Encasement β Adds extra time & labour for breaking concrete.
β Traffic Control β If work is near a road or footpath, extra permits & management costs.
β Deep Excavation Challenges β Requires larger machines, extra shoring, and more crew.
β Disposal Costs β Any cut concrete, steel casing pieces, or grout-filled sections must be removed.
β Unforeseen Delays β Always include qualifications in the estimate to allow for variations.
4οΈβ£ Key Takeaways for Estimating Accurately
β Site Conditions Matter β Confirm depth, access, and encasement status before pricing.
β Excavation & Support Systems β Shoring, shields, or benching costs must be included.
β Cutting & Reinforcement Costs β Allow extra costs if existing pipe has steel casing or grout fill.
β Testing & Compliance β Sydney Water requires compaction testing for reinstatement.
β Clearly Define Qualifications β State that the price is based on a non-encased sewer line unless proven otherwise.
π Need expert estimation? Contact WSE Sydney
π§ tenders@watersewerestimatingsydney.com.au
π +61 451 404 645
